Dalles Spill Close Out Statement
Transformer unit T2B had secondary containment, but the inadequate sealing of
the expansion joint in the containment allowed oil to drain to the roof behind
the transformer, thence to the roof drain which was piped to the lower part of
the dam in the tail race. It was via this path that the 1,900 gallons of oil
which ultimately reached a point about 40 miles downriver of The Dalles Dam
reached the water from unit T2B.
Based on the information gathered, Ecology determined the immediate cause of
the spill was as follows:
Structural Failure – The flexible material used to seal the expansion
joint in the secondary containment of unit T2B no longer maintained the
integrity of the containment, resulting in oil draining to the downstream side
of the dam via the roof drains.
Based on the independent assessment report requested by the dam operator,
Ecology determined the contributing factors to the spill were as follows:
Snow—The combination of rock on the roof and the covering of 1 ft of snow
masked the fact that oil was on the roof.
Temperature—The cold weather triggered the freezing of the water
remaining in the cooling water pipes within the transformers, and caused breaks
in the cooling water pipes.
Structural Failure—The cooling water piping of units T2B and T2C suffered
multiple breaks as the result of the cold temperatures.
Inadequate Planned Maintenance Program—
Age and condition of transformer and cooling water system.
The water side of the transformer cooling system was not drained when it
was isolated.
Cold weather plan does not address isolated transformers.
Cooling water isolation valves were stuck and could not be operated.
The transformer storage tank level gauges do not work and they did not have
an inventory of their current capacity.
Infrequent and non-specific operator required inspections and improper
isolation of the…secondary containment.
Inadequate Procedure/Policy—Transformer inspections are only once per
week....
Insufficient Personnel—Transformer inspections…may be omitted if busy.
Independent Review
The Ecology Spills Program contracted for an
independent review of this spill to capture high value lessons learned.
Real-world spill responses are infrequent and costly and Ecology is constantly
looking for opportunities to maximize its learning.
This report provides another valuable learning tool.
Cleanup of the Dalles Oil Spill Was
Delayed
Oil Spill Management
On Thursday, January 15, 2004 the Corps of Engineers reported
that the Dalles Dam had experienced an oil spill of less than 25 gallons.
Ecology’s On-Scene Coordinator (OSC) and his deputy OSC immediately responded to
the scene from the Yakima regional office. Because of concerns regarding the
Corps’ past spill reporting practices and uncertainty about the current spill,
the Ecology Spill Team brought in an additional highly experienced investigator
on the following day to assist the Corps in its investigation and to help
determine the actual volume of oil spilled.
The “less than 25 gallons” initially
reported, far underestimated the actual volume of oil spilled. It was not until
Ecology personnel flew over the River on Saturday that the full extent of the
oil slick was known (see the above photograph taken during the flight). It was
eventually determined that a total of about 2,050 gallons of transformer oil
containing PCBs had entered the river. The lack of an accurate spill volume
during the early stages of the spill incident made it very difficult to properly
manage the spill response, and to deploy enough clean-up equipment and
personnel.
Other problems also affected the
initial clean-up. Oil spill containment and recovery boom was not placed in the
river until 6 hours after the spill was identified, there was a shutdown of
response operations on Thursday night because of safety concerns, and the Corps’
incident management team was under staffed and did not provide adequate support
for the Unified Command. Information was also not always released in a timely
manner. By the time the actual volume of the spill was established, most of the
oil had already moved downstream and was no longer recoverable.
During the early stages of the spill,
Ecology ramped-up its response capability by sending additional personnel to the
dam. By Sunday, Ecology had 12 members of its spill team on scene.
Future Oil Spill Response Planning
While they were not well prepared for this incident, the
Corps has since committed to acquiring and staging oil spill containment booms
at the dam. They have also committed to training employees to deploy spill
recovery equipment in the river during maintenance operations and in response to
spill emergencies. The Corps’ program will require periodic training and
practice to maintain an adequate state of readiness, but the benefits should far
exceed the costs. The Department of Ecology stands ready to help the Corps
develop an effective program, but has not yet received a request for assistance.
The Transformer Oil Contained PCBs
The Department of Ecology intends to
fully examine the PCB implications of this spill and make sure that concerns are
properly addressed. Several important points on the PCB issue follows.
• While low levels of PCBs are ubiquitous in the environment from past
industrial practices, it is the goal of the Department of Ecology to eliminate
any new sources of PCB, and to reduce the ambient concentration to the lowest
possible level.
• The production of PCBs has been banned in the United States since 1977. PCBs
are persistent toxic chemicals that can bioaccumulate in fish and other
organisms with the potential to cause human and environmental health problems.
The threshold concentration that can cause human effects is not fully
understood.
• Ecology has adopted a strategy to address Persistent Bioaccumulative Toxicants
(PBTs) such as PCBs. Ecology is working during the 2004 legislative session to
obtain additional funding for this effort. Governor Locke’s budget proposes an
additional $436 thousand for this work.
• The total amount of PCBs in the oil that was spilled (reported to be 8.0
milligrams per liter of oil) was not large in everyday terms. However, because
they are PBTs Ecology is very concerned about the potential long-term impact of
the spill. It is interesting to note that the current EPA limit on PCBs in
drinking water is 0.0005 milligrams of PCBs per liter (0.0005 mg/L). We do not
want any of our state’s waters to even approach this concentration.
• The U.S. Agency for Toxic Substances and Disease Registry (ATSDR) web site is
good source of information on a number of human health problems caused by PCBs.
This web site can be accessed through the link provided under “Other Sources.”
Among other issues, the web site discusses the neurobehavioral and developmental
deficits that have been documented in newborn babies that were exposed to PCBs
through their mother’s diet, which included fish with moderate to high PCB
content.
• In addition to reproductive and developmental effects; PCBs can affect the
skin, endocrine organs, the liver, likely cause cancer, and adversely affect the
cardiovascular, immune, musculoskeletal, and gastrointestinal systems.
Many questions remain regarding
environmental contamination as a result of the spill. Ecology has asked the
Corps to submit and implement a sampling plan to determine the extent of PCB
contamination in Columbia River sediments, river water, and fish. As of March 4,
2004 (seven weeks after the spill), the Corps had not submitted their sampling
plan to Ecology. Every day that passes reduces the value of the environmental
sampling effort.
The Dalles Oil Spill Was Preventable
After the spill, the Corps convened an independent panel of
experts to determine the cause of the spill. On February 9, 2004 the evaluation
panel concluded that maintenance and inspection procedures, and the condition of
old equipment contributed to the spill. The panel also determined that the
transformer's water-based cooling system should have been drained when the
transformer was taken out of service in October 2003. Among other things, they
concluded that the immediate cause of the spill was a water pipe that cracked
during freezing weather. The report was prepared by: Mitchell Samuelian, U.S.
Bureau of Reclamation, Denver, Colo.; Gary Sanford, Bonneville Power
Administration, Portland, Ore.; and Jim Blankenship, U.S. Bureau of Reclamation,
Glen Canyon Dam, Calif. (retired). Ecology is encouraged that the Corps of
Engineers’ initiated the investigation that identified deficiencies with the
ultimate goal of preventing future spills. Also encouraging, was Corps of
Engineers’ Portland District Operations manager Deborah Chenoweth’s commitment
to immediately begin addressing the issues that were identified. Ecology plans
to work with the Corps to ensure that these and other changes are implemented.
Ecology’s investigation is still underway.
The Dalles has 2 Additional Spills in February
Monday, February 23, 2004
On Monday, February 23, 2004 another spill occurred when
maintenance crews “spun” the turbine in main generating unit No. 3 in
preparation for maintenance work. When the turbine was rotated, oil trapped in
that unit was discharged into the Columbia River downstream of the dam. The
Corps reported that about 15 gallons mineral oil was discharged.
Friday, February 27, 2004
The Corps reported a spill on February 27, 2004 that they
estimated to involve “upwards of 50 gallons of oil.” The oil sheen was reported
to cover an acre-sized area of the Columbia River downstream of the dam.